Owner: Venice Energy
Location: Port Adelaide, South Australia Capacity: 1.1 mtpa Cost: $200m Software: Primavera P6 |
One of the world's first floating LNG import terminals, powered by 100% renewable energy. Project Control provided planning & scheduling to assist development of a floating storage & regasification unit-based import terminal in Port Adelaide, Australia.
Venice Energy anticipate the project to be commissioned by the first quarter of 2027. |
|
Achievement: Return to service within 9 months
Client: NCIG Builder: FLSmidth Location: Newcastle, NSW Software: MS Project |
One of NCIG's two shiploaders was blown off its rails and damaged on November 16 2020, which caused the terminal to have a 30% reduced export capacity. Project Control Pty Ltd were engaged to develop a recovery program with FLSmidth with the aim of returning the damaged shiploader to service as fast as possible.
It was quickly established that a full replacement taking approximately 18 months would not satisfy this requirement. A repair strategy was implemented resulting in a return to service within 9 months. |
|
Achievement: Completed 6 months early
Total Project Value: $90mil Location: Newcastle, NSW Completion Date: Sep 1998 Software: Primavera P6 |
This was our 1st project working for Port Waratah Coal Services, and were responsible for the development of contract schedules. A joint venture company on behalf of PWCS managed the construction of a 3rd Shipping Berth as part of the expansion of the Coal Loading Facility.
We had a number of obstacles to overcome on this project, in particular a very short time frame of 9 months, a tight budget, EPA requirement regarding the dredged material, underwater bank slippage after initial dredging was completed, as well as the usual contractor claims and delays. Scope for the project included;
|