Project 3Exp (Stage 3 Expansion) PDF Print E-mail
pwcs
bechtel

 

Start Date Oct 04
End Date Expected OCT 2007 – Current Target APR2010

 

Providing Cost and Planning assistance from Feasibility Study thru to Project Completion.   This is the 3rd project with PWCS and 5th with Bechtel.

The project involves the construction of Conveyors, Transfer Houses, Berm and Pad utilising a combination of Preload and Dynamic Piling, all intended to increase PWCS capacity from 90mil to 110 mil t/year.

The Project Schedule is developed in Primavera P3 and has 5 Sub Projects;

  • Engineering
  • Procurement/ Contracts
  • Construction
  • Commissioning
  • Tie-Ins

The Schedule is updated on a weekly basis including;
  • Critical Path by Trade
  • 2 week look ahead
  • Earned Value and % Complete Analysis
  • Manpower Histograms and Productivity Analysis
We are currently assessing all areas of opportunity to fast track the project in every area, in an attempt to bring the project in 10 months early (from 28months to 18 months).
 