Start Date January 1997
End Date December 1998 (24 month project)

 

This was my first Defence Project with ADI.

I joined ADI initially to develop their Integrated Logistics Support (ILS) schedule in Artemis Views for approval by the Navy (within a 3-month period).  I was able to successfully deliver a detailed ILS (Integrated Logistics Support) schedule within the required 8 week time frame to the Project Authority without previous experience in using Artemis.  This schedule was accepted as the first baseline and I continued on with ADI for a total of 24 months until the first ship was launched, and the ILS program was complete.

My duties were to provide full Earned value Analysis to the Navy on a monthly basis and to maintain the schedule which required a thorough knowledge of each and every system on the new Minehunter Vessels.

I also developed an MML (Master Materials List) for the project, which provided a useful inter-department cross-reference and data store for every part on the vessels.

 




© Steve Church Project Control, 2009



Created using Joomla!. Layout design by SiteGround

Valid XHTML and CSS.