Liddell Coal Expansion PDF Print E-mail
downeredi
xtrata

 

Start Date Feb 2007
End Date July 2008

 

Provided Planning using Primavera P3 from Engineering thru to procurement and Construction.

The Project included the Design and Construction of a 100t/h Coal Prep Plant and associated ROM/RAW/Product and Reject Conveyors.

The Project Schedule is developed in Primavera P3 and has 3 Sub Projects;

  • Engineering
  • Procurement/ Contracts
  • Construction

The following subprojects were handles directly by the Client;

  • Commissioning
  • Tie-Ins

The Schedule is updated ‘live’ on site on a weekly basis including;

  • Critical Path by Trade
  • 3 week look aheads
  • Earned Value and % Complete Analysis
  • Manpower Histograms and Productivity Analysis

Our role was to get the Project to Mechanical Completion by 21MAY08, which required us to accelerate the construction phase from 10 months to 7 months.  The weekly focus on Schedule allowed all parties (eng/proc/subcontractors) to see the impact their decisions were having on others.  Despite the many hurdles along the way, it was a pleasing result to have achieved this difficult milestone.

 